Since late summer, crews south of Broulim's have been leveling ground and cutting a turnoff from Highway 33. Earlier this month, Teton Valley News reported that three projects were planned for the site: a four-story hotel, a new city street, and a Circle K gas station. The city's project pages, last updated October 19, 2026, now list the Circle K applications as withdrawn.
That leaves two projects. The street is going in first. The Marriott Element hotel behind it is aiming for summer 2028. The South Main Street frontage, where the gas station would have stood, has no announced use.
The street is the first thing being built
The new road is Harrop Avenue, a public street that will run west from Highway 33 along the south side of the property. The city required it as a condition of the hotel approval. Plans filed in February show sidewalks on both sides, landscaped strips, and 17 street trees, plus one shared entrance off Harrop serving the lots behind it.
The order of work was the developer's choice. In its site development file for the public improvements, the city says the applicant asked to submit the project in two pieces "to start construction of the public improvements as quickly as possible." That first piece covers Harrop Avenue, the water, sewer and utility lines under it, and the street trees. The hotel has its own separate application.
No completion date has been given for Harrop Avenue or the Highway 33 turnoff. Right now, the work you see from the Broulim's parking lot is the start of a street.
A hotel that has been "planned" since 2022
The Element first went through Driggs's review process in 2021, and this fall is the first time ground has been moved for it. The owner of the land south of Broulim's is Lot 6 Development Group, a Salt Lake City firm whose partner Tyson Cichos has been the public voice of the project throughout. Here is the sequence, using the records and coverage available:
- 2021 to May 2022. The hotel went through design review. Teton Valley News reported that the Planning and Zoning Commission conditionally approved the 107-room, four-story design on May 11, 2022, and that the Idaho Transportation Department gave conditional approval the next day.
- More than a year later. The approvals lapsed. The Jackson Hole News&Guide reported that city planning staff said Driggs planning and zoning permits expire after one year, no building permit had been issued, and the project would have to go back through design review.
- Early 2026. Because the building's exterior hadn't changed, the city decided the project could resubmit to confirm site development conformance instead of starting over. The developer filed the street and the hotel as two separate applications.
- Fall 2026. Dirt started moving, and the city approved the hotel's site plans shortly before Teton Valley News reported on the site this month.
When the project looked stalled, Cichos told the News&Guide what had held it up:
"We are still proceeding with the Marriott Element in Driggs. We are finalizing design with Marriott. Construction pricing and interest rates will dictate ultimate timing… It was construction prices and interest rates that slowed the project down."
The approved plans call for 107 rooms, 67 of them with kitchenettes, along with a restaurant, a bar and lounge, and a pool and patio, on 2.2 acres. The two sources give different parking counts. Teton Valley News reports 102 off-street spaces, while the city's hotel site development page lists 106. Cichos told Teton Valley News that Lot 6's target opening is summer 2028.
The Main Street parcel is empty again
The Circle K was planned for the part of the property most residents will notice, the lot facing South Main Street in front of the hotel. This is the second time the application has stalled. A sketch plan design review submitted in 2024 expired in July 2025. In August 2025, the city approved a split of the original 13.10-acre parcel, which by the city's figures produced a 2.15-acre lot and a 10.91-acre lot. The Circle K application then came back for the smaller piece.
Before the withdrawal, this is what had been proposed for the 2.15-acre lot:
Element | What the application proposed |
|---|---|
Building | 5,000 square feet, with a convenience store and an attached quick-service restaurant |
Fuel | Six pumps under a canopy of similar size |
Driveway | 39 feet wide, where city code allows 32 for a two-way commercial driveway |
Traffic | About 3,900 vehicle trips a day, up to 320 in the busiest evening hour, by city staff estimate |
Access | A shared entrance off Harrop Avenue, after staff recommended dropping a connection through the Broulim's lot that would have removed 18 parking spaces there |
The application had made some progress. On June 30, 2026, the city's Design Review Advisory Committee recommended approval with conditions. The Planning and Zoning Commission would have made the final decision. The 39-foot driveway required a separate variance. The project's engineer, Vincent Kelly of Colliers Engineering & Design, wrote in an August 18 letter that fuel tankers and delivery trucks need that width to turn in and out safely.
Neither request reached that commission. The city's DR25-6 design review page and its VAR26-1 variance page, both last updated October 19, 2026, list each application as withdrawn before a final decision and say no further review will occur. Neither page gives a reason for the withdrawal, and no other use has been announced for the 2.15 acres.
The lot is still zoned CX, Commercial Mixed Use, and is inside the city's Design Review Overlay. Any future proposal for the Main Street frontage would go through the same design review process that is listed on the city's project pages.
What still has to happen before the hotel opens
Approval of the site plan doesn't clear every step. Teton Valley News lists two conditions the developer has to meet before the hotel can open, and earlier coverage mentions highway requirements that haven't been publicly updated since:
- Water rights. The approval includes a condition on water rights.
- Height and workforce housing. The building can exceed Driggs's 35-foot height limit through the city's Qualified Workforce Housing Incentive Program. In return, the developer has to either place a deed restriction on a studio apartment in Front Street Lofts or make a payment in lieu. The May 2022 coverage described the hotel and Lot 6's Front Street mixed-use project as unrelated, with no units reserved for hotel staff. If the developer chooses the deed restriction over the payment, the 2026 approval will tie the two projects together through that studio.
- The highway. The News&Guide reported that the Idaho Transportation Department had required Main Street to be widened at the site and possibly a new stoplight, which would give Teton Valley three. No public update on either requirement has appeared since then. The Highway 33 turnoff now under construction is the only highway work at the site that has been reported this fall.
The rest of the property is also an open question. The larger parcel from the 2025 split remains alongside the Circle K lot. The hotel's 2.2 acres sit behind the Main Street frontage on the west side. The filings cover the street and the hotel. Nothing has been filed for the remaining land.
What to watch for on South Main
Over the next few months, the visible progress will be the street: curbs, utilities, sidewalks and the 17 trees along Harrop Avenue. Lot 6 still has to meet the water-rights and workforce-housing conditions before the hotel can open, and nothing will be built on the Main Street frontage until a new application is filed. The city posts each application on its project pages with a last-updated date, and those pages are where the Circle K withdrawal appeared.
Driggs posts every commercial application along South Main on those public project pages, from sketch plan through final decision. If you own land along the Highway 33 corridor and want to understand how a project like this one affects your parcel's options, the team at Wealthwise Real Estate would be glad to talk it through with you. Contact Us.